Bay Area Rapid Transit District - BART Transbay Tube Support
Manson's Barge & Dive Platform
Global is providing diving assistance in the removal and replacement of anode cable and anode arrays for the BART transbay tube. The work is being performed as part of ongoing maintenance for the tube. The divers are utilize dredges and airlifts with the derrick assistance to remove up to 30’ of bay mud covering the tube to access cable penetrations. Fourteen of the anode arrays are schedule to be replaced in depths down to 130 feet. Project challenges are the bay currents and the water depth.
Project Updates
Project Details
We are providing diving assistance for the replacement of 14 anode array assemblies used for the protection of the BART Transbay Tube.
March 1, 2010 - Present
Manson Construction