Chevron - Hurricane Recovery Team
SAT I situated on the BOA Deep C
This saturation diving project included the removal of structural debris, as well as wedding cake and wellhead operations. The work was conducted across six platforms with 29 wellhead installations, ranging in depth from 120-280 feet of sea water (fsw).
Project Details
Conducted a saturation diving project, including structural removal, wedding cake and wellhead operations.
March 1, 2007