PROJECT DETAIL
Global performed work on a pipeline riser in the Cook Inlet. The project required the use of two hydraulic guillotine saws, hydraulic grinders, and impact wrenches. We “fresh headed” the pipeline using a torque connector, then had the associated spool piece measured, manufactured, and installed during a six day period. The subsea portion of the project was completed four days ahead of schedule.